County considers data center project, advances moratorium

Posted

A potential data center project is being considered for an existing building in a Clarendon County industrial park and could move forward once an ongoing power study is completed.

Clarendon County Economic Development Executive Director George Kosinski told County Council Aug. 10 that the project would convert an approximately 100,000-square-foot building owned by Santee Electric Cooperative into a 15-megawatt data center.

The project is not final. Kosinski said the entity behind it has paid for a study to determine whether Santee Cooper can provide the required power at the site within six months.

If sufficient power is available, the entity could finalize the agreement and begin construction, which is expected to take eight to 12 months.

Chairman Jay Johnson said a data center that meets the county’s requirements for an industrially zoned property would not come before council for a vote unless the entity requested tax incentives.

“If they meet all the criteria to put it in the industrial park, and they don’t come to us asking for any tax breaks, it never even goes before us,” Johnson said. “We don’t get to vote on that.”

The entity is not seeking county incentives and would pay standard property taxes, Kosinski said.

The facility could create approximately 28 permanent positions paying between $100,000 and $130,000 annually, along with security, heating and air conditioning maintenance and other supporting jobs. Approximately 200 people could be employed during construction.

As the potential project moves forward, council gave first reading to a six-month moratorium on most applications for data centers and battery energy storage system facilities while officials develop regulations governing the uses.

The moratorium would apply outside areas zoned Industrial I or Industrial II. Because the potential data center would be located in an existing industrial park, it would not delay or prevent the project.

The moratorium will not take effect unless it receives third and final reading.

The Planning Commission unanimously recommended the measure Aug. 3 because the county’s Unified Development Code does not specifically define the facilities or identify where they may operate.

During the six-month period, Planning Department staff and the commission would study where the facilities may be appropriate and recommend development standards. Council could extend the moratorium by resolution.

During public comments, Summerton Councilwoman Elaine Wood asked council to examine the potential effects of data centers on electricity costs, water supplies, noise and public health.

“I’m just asking y’all to look into this, really research it more than what I have,” Wood said.

County officials said the proposed facility would use a closed-loop cooling system. Kosinski said the system would initially require about 40,000 gallons, while the facility’s maximum daily water use would be approximately 8,000 gallons.

Manning’s water system has approximately 3.2 million gallons of excess daily capacity, he said.

Kosinski estimated noise would remain below 60 decibels at the property line because the equipment would be housed inside a building with insulated concrete walls.

County Administrator Walt Ackerman said the potential project reached the county because the privately owned building was being marketed in an industrial park. The county did not actively recruit a data center.

“We don’t have a lot of safeguards in place for something like this,” Ackerman said, explaining the need for updated regulations.

Councilman John Coker said the moratorium is intended to prevent the facilities from being placed near homes while continuing to allow them in industrial districts.

Council also gave second reading to an ordinance that would provide Clarendon County boat owners with the full property tax reduction authorized under a new state law beginning Jan. 1, 2027.

Act 109, signed by Gov. Henry McMaster on March 30, exempts 42.8571% of the fair market value of qualifying boats and watercraft from property taxes. The full exemption effectively reduces the assessment ratio from 10.5% to 6%.

State law phases in the exemption over three years, beginning with 14.2857% in 2027 and increasing to 28.5714% in 2028 and 42.8571% in 2029. Clarendon County’s ordinance would apply the full exemption in 2027.

Ackerman said the county is financially able to absorb the reduction immediately.

“We’re just going to jump from 10½ all the way down to 6,” Ackerman said. “It’s going to cut everybody’s taxes almost in half.”

The law also treats a boat and any affixed outboard motor as one unit for property tax purposes. The exemption does not apply to watercraft classified as a primary or secondary residence.

The ordinance requires third and final reading before taking effect.

In other business, council gave second reading to an amendment to the county’s 2025-26 budget after officials projected an approximately $680,000 general fund surplus.

The county originally expected to use $1.5 million from its fund balance but avoided doing so through cost-saving measures, Ackerman said. The amendment would transfer $201,000 of the surplus to debt service to prevent a millage increase and approximately $500,000 to capital projects to reduce the need for additional debt.

Council gave second reading to a Freedom of Information Act policy and fee schedule that includes a $5 minimum charge, 25 cents per paper copy and the actual cost of staff time and electronic storage media.

Council also gave first reading to an ordinance requiring certain qualifying economic development projects to direct 20% of county property tax revenue to an infrastructure fund for five years.

Another ordinance receiving first reading would convey a small portion of county property near the Clarendon County Health Department to the City of Manning for its planned park.

Council granted final reading to rezone an approximately 6.2-acre parcel at 5474 Greeleyville Highway from Industrial II to Agricultural II.

Council also recognized five employees for their service: Detention Center Lt. Braxton Murray and Master-in-Equity Judge Joseph Coffey, 10 years each; Drug Court Judge Amy Land, 15 years; Emergency Management Assistant Director Susan Thomas, five years; and Sheriff’s Office school resource officer Jonathan Coker, 20 years.